Job @ Bakri – Progress of WoRks

Preparation of timber formworks for the construction of pile caps.
The steel bars for the pilecaps and column stumps are ready for the Clinic Block.

Piling is 70% completed; pending cutting of pile heads for the construction of pilecaps at the Clinic Block.

Delivery and un-loading of pre-cast concrete piles on the site.